This guide covers the installation of T Home WPC decking boards on a levelled support frame with concealed clips. Read it in full before cutting the first board. If anything on site differs from this guide — an uneven base, a heavier load, a board length you did not order — stop and confirm with us before you fix. Boards, clips, screws and trims are supplied as one kit; use the parts matched to your board.

1 Tools and materials

No special tools are required. T Home decking installs like timber, with standard woodworking tools.
  • Tape measure; spirit level (600 mm or longer); 2 m straight edge: T Home WPC decking boards
  • Circular saw or mitre saw with a fine-tooth blade: Starter clips, decking clips and wing clips, with matching screws
  • Drill / driver; 3 mm drill bit for pilot holes: Joists — WPC battens, timber or steel, to local code
  • Rubber mallet; 5 mm spacers: Joist support parts (U-clips, cross joints) where the base needs them
  • Pencil and string line: Edge trims / end caps; L skirting where the edge is exposed
Clips and screws are matched to each board and joist section and are supplied as a set. Do not mix clips from another system: the clip sets the 5 mm gap.

2 Storage and handling

  • Store boards flat on a solid, level surface, on bearers at 600 mm maximum centres. Bearers must sit under the board ends as well as the middle.
  • Do not stack more than eight pallets of deckboards, or more than 15 lengths of loose boards in one stack. Keep loose boards straight and neat.
  • Store boards off wet ground and out of direct sunlight. Keep them dry until they are fixed.
  • Check the delivery on arrival: model, colour and quantity against the order. Report any damage before installation starts.
  • Carry boards on edge or with two people. Do not drag them across rough ground.

3 Safety

  • Always wear gloves and eye protection, and work in a well-ventilated area.
  • Wear goggles when pressure washing or scrubbing.
  • Do not burn off-cuts. Dispose of them with general building waste.
  • Keep children away from the work area until the job is finished and tools are stored safely.

4 Golden rules

These rules come from hands-on experience and long use. Keep them in mind through the whole job.
  • Always pre-drill before screwing.
  • Make sure the support structure is strong and levelled.
  • Allow the gaps — board to board, end to end, and board to any solid object.
  • Reduce the span where the deck will carry a heavier load than normal.

5 Drainage and ventilation

A deck that cannot drain will not last. Prepare the ground before the frame goes down.
  1. The site must drain freely, or fall at a gradient of 1 in 40 so water runs off.
  1. Remove turf and at least 100 mm of topsoil where the deck will sit.
  1. Replace the topsoil with gravel or hardcore.
  1. Lay a weed barrier, covered with a light layer of pea shingle.
  1. Leave at least a 50 mm drainage gap all round the substructure.
  1. Give the finished deck a slight fall — at least 2 mm per metre — for drainage.
  1. Make sure skirting does not block airflow under the deck.

6 Support structure and joist spacing

Every T Home deck is built on a code-compliant substructure. Set the frame first and get it level: the boards can only be as flat as the frame under them.
  • Frame centres are 300–400 mm.
  • Every board must rest on at least three supports.
  • Never fix deckboards directly to a solid surface.
  • Fix the joists to the base first, with expansion anchors (nylon plug + screw): drill through the joist into the concrete, tap in the plug, drive the screw down. No board goes on until the joists are fixed and level.
  • Fix all joists level and centred. Check with a 2 m straight edge.
  • Where the ground or the base needs it, fit a joist support system under the frame: U-clips for lateral take-off and cross joints where tubes cross, sized and combined to the substrate and the project.
  • Where battens cannot be fully supported, use a solid structure of another material (timber, aluminium or steel). For elevated decks, joist spacing and materials must comply with local and national building regulations.
  • When battens are used as the frame material, the same care applies:
  • The substructure must sit on solid, level ground.
  • Battens are supported 50 mm from the ends; two supports are required where a batten is longer than 500 mm.
  • Fastener spacing is 700 mm maximum.
  • Batten end-to-end and end-to-side gaps are 5–20 mm; batten end to a solid object is at least 10 mm; batten side to a solid object is at least 5 mm.

Span adjustment

The span is the distance between joists. Shorten it when the boards run at an angle, or where they will carry extra load or heat.
  • 90° (perpendicular): Normal — 300–400 mm centres
  • 60°: 50 mm less than normal
  • 45°: 100 mm less than normal
  • 30°: Half of normal
  • Hot areas (hot tub, sauna): 100 mm less than normal
  • Heavy load: Reduce the span accordingly
Board ends may overhang the last joist by 30 mm maximum.

7 Deckboard gapping

Gaps are not mistakes. They let water drain and let the boards expand and contract with temperature.
  • Side to side (between board sides): 5 mm
  • End to end (between board ends): 5 mm
  • End to a solid object (wall, skirting): 5 mm minimum
  • Side to a solid object: 5 mm minimum
The clip sets the joint: seat the clip in the groove and the gap follows. Do not butt boards tight — a deck fixed tight in cool weather will buckle when it warms up.

8 Fixing with concealed clips

  1. Fix the starter clip along the first edge; it holds the first board.
  1. Seat the first board in the starter clip and check it is level.
  1. Slide a decking clip into the groove of the board and screw it to the joist. Use the wing clip where the detail calls for it.
  1. Pre-drill before driving any screw through a board.
  1. Drop the next board onto the clips and tap it home with a rubber mallet against a scrap block. Do not strike the board face directly.
  1. Work across the deck one board at a time, checking level every few boards.
No screw goes through the face of a board. The fixing is hidden in the groove, so the walking surface stays clean.

9 Trimming and finishing

  • Cut boards with standard woodworking tools; a fine-tooth blade gives the cleanest edge.
  • Overhang: board ends 30 mm maximum, board sides 9 mm maximum.
  • Close every cut end with an end cap or skirting so no cut core stays visible.
  • Fix edge trims and L skirting with screws driven directly through the trim face — decking and cladding trims fix the same way.
  • Keep fasteners at least 20 mm from the edge of a board, staggered in a zigzag pattern along the run.
  • Gapping rules apply to skirting boards as well as deck boards: at least 5 mm at end joints and 3 mm at sides.
  • Make sure skirting does not block airflow under the deck.

10 After installation

  • Level: All boards flat, no rocking or hollow spots.
  • Gaps: 5 mm gaps even at every joint.
  • Fixings: All clips seated; no screw through a board face.
  • Ends: Cut ends closed with caps or skirting.
  • Drainage: Fall present; airflow under the deck clear.
  • Site: Swept clean; off-cuts removed.
Care: sweep the deck regularly. Wash with clean water and a soft brush. If you pressure wash, keep the nozzle back from the surface and wear goggles.
Questions or a quote for your next order: eva@thomestyle.com · WhatsApp / WeChat +86 15956288470 · www.thomestyle.com — send the model, colour and quantity; we reply with a quote within 24 hours.

Read next

More from T*Home

Installation guides and material notes for WPC decking, wall cladding and fencing.